Case 01
Palm oil mill, Kimanis
- Symptom
- Unplanned steam-line failures, three in eighteen months, each stopping the mill mid-crop.
- Finding
- Under-lagged sections running wet. Corrosion under insulation along 1.2 km of the header.
- Fix
- Full header replacement staged across the low-crop window.
- Readout
- 1,200 m replaced. Changeover completed in 9 days against a 21-day plan. No unplanned steam-line downtime in the 31 months since.